試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

Four months into a 10-month project, the project manager realizes that the project is behind schedule and slippage will lead to an overrun of 25% of the project’s budget. A change request is created, but when the project manager seeks approval, the executive is reluctant to do so. What could be the reason for this executive’s reluctance ?
A、Lack of the project management plan approval.
B、 Lack of the risk management plan approval.
C、 Lack of the communications management plan approval.
D、 Lack of the change management plan approval.


相關試題