The project management office completes a year-long asset management project for a customer. The customer requests the project be extended to incorporate recently acquired assets. Which of the following should the project manager do next ?
A、Present the change order to the change control board
B、Review and analyze the customer’s a change request
C、Refuse to accept the change order and complete the initial work scope
D、Issue a counter-proposal for the customer’s consideration