在线男人天堂|韩国三级电影未删减版|色戒未删完整版西瓜影音|亚洲一二三四,一路向西粤语在线观看完整版电影,伊人网站在线观看,成人免费观看高清视频

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

You’ve been assigned to take over managing a project that should be half complete according  to the schedule. After an extensive evaluation, you discover that the project is running far behind schedule, and that the project will probably take twice the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action?
A、Try to restructure the schedule to meet the project deadline .
B、Report your assessment to the sponsor.
C、Turn the project back to the previous project manager.
D、Move forward with the schedule as planned by the previous project manager and report at the first missed milestone.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容