A project to implement a new system has trouble launching due to extensive and contradictory discussions regarding the project deliverables. The project manager leaves the company, and a new project manager is assigned to the task.What should be the first action for the new project manager?
A、Formalize the project management plan and communicate this to relevant stakeholders
B、Escalate to the project sponsor and request support in handling the ongoing discussions.
C、Develop a work breakdown structure and communicate this to all relevant stakeholders.
D、Formalize a project charter and request approval from the sponsor and key stakeholders.