試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(7)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

You prepared an integrated project plan and a project schedule. You submitted it to the steering committee and it was approved. Key stakeholders accepted the plan. It is time to distribute it. Both the project plan and schedule should be distributed to
A、All stakeholders in the performing organization
B、All project stakeholders
C、Project team members and the’ project sponsor
D、People noted in the communications management plan